Video: Scheduling a Kitchen Remodel

The question has been issued to me about planning. Once we decide, for instance, on a kitchen remodel when should we actually start the project? Well, obviously at that stage you've come to an agreement on price, you submitted for permits the next thing to consider before you start the project is when the long lead items will be done, and the long lead items are basically The count, cabinets, custom cabinets, countertops any sinks, fixtures that are coming from far away.


Those are long lead items. You want to have a schedule that lets you know when those items are going to be available. And you don't want to start your construction until those items have been delivered. Otherwise, your kitchen is demolished and not usable too far in advance. It could be a much more comfortable process.


So that's what I would say. As far as the process of when to start the job.